Assessment Year | 2021 |
---|---|
Principal Product | Treated Wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | less than $500 k |
# of Employees | 12 |
Plant Area |
1,307,000
ft2
|
Annual Production | 2,920,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $393,882 | 10,612,800 |
kWh
|
$0.037 |
Electricity Demand | $310,434 | 18,432 |
kW-mo/yr
|
$16.84 |
Electricity Fees | $87,003 | - |
|
- |
TOTAL YEARLY COSTS | $791,319 | |||
RECOMMENDED SAVINGS* | $243,519 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,498 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $231,021 | $2,706 |
$149,821
3,745,517
kWh
|
$81,200
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,048 | $811 |
$5,298
132,442
kWh
|
$2,750
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,453 | $8,113 |
$1,769
44,214
kWh
|
$908
-
kW-mo/yr
|
$(-224.0) | |
04 | 2.7135: Install occupancy sensors | $1,279 | $1,850 |
$1,279
31,966
kWh
|
- | - | |
05 | 2.7272: Install heat pipes / raise cooling setpoint | $718 | $38 |
$317
7,944
kWh
|
$401
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $243,519 | $13,518 |
$158,484
3,962,083
kWh
|
$85,259
-
kW-mo/yr
|
$(-224.0) | ||
TOTAL IMPLEMENTED | $12,498 | $10,812 |
$8,663
216,566
kWh
|
$4,059
-
kW-mo/yr
|
$(-224.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs