ITAC Assessment: LE0607
ITAC logo
ITAC Assessment: LE0607
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Animal feeds
NAICS 311119: Other Animal Food Manufacturing
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $100
M
to 500
M
# of Employees 96
Plant Area 100,000
ft2
Annual Production 125,000
ton
Production Hrs. Annual 8,736
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $311,184 3,896,697
kWh
Electricity Demand $43,776 10,840
kW-mo/yr
Electricity Fees $79,743 -
Natural Gas $118,798 25,844
MMBtu
TOTAL YEARLY COSTS $553,501
RECOMMENDED SAVINGS* $2,090,273 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Primary Product Savings Increase in Production Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,048 - $1,915
23,937
kWh
$133
-
kW-mo/yr
- - - -
02 2.4226: Use / purchase optimum sized compressor $138,699 $35,000 - - - - - $138,699
03 4.514: Re-arrange equipment layout to reduce handling costs $1,005,000 $300,000 - - - - - $1,005,000
04 2.4321: Upgrade obsolete equipment $833,198 $400,000 $(-1,040.0)
(-13,000)
kWh
$(-242.0)
-
kW-mo/yr
- - $834,480 -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $24,953 $13,000 $20,442
255,528
kWh
$4,511
-
kW-mo/yr
- - - -
06 2.2113: Repair or replace steam traps $3,892 $4,700 - - - $3,892
-
MMBtu
- -
07 2.2442: Preheat combustion air with waste heat $4,764 $10,000 $(-872.0)
(-9,776)
kWh
$(-109.0)
-
kW-mo/yr
- $5,745
-
MMBtu
- -
08 2.9112: Use solar heat to heat water $77,719 $482,154 $59,425
742,815
kWh
$486
-
kW-mo/yr
$17,808 - - -
TOTAL RECOMMENDED $2,090,273 $1,244,854 $79,870
999,504
kWh
$4,779
-
kW-mo/yr
$17,808 $9,637
-
MMBtu
$834,480 $1,143,699
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs