Assessment Year | 2025 |
---|---|
Principal Product | Gaskets, seals, and vibration isolators |
NAICS | 326291: Rubber Product Manufacturing for Mechanical Use |
SIC | 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
60,000
ft2
|
Annual Production | 12,500,000
pieces
|
Production Hrs. Annual | 7,280
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $124,223 | 1,387,834 |
kWh
|
$0.090 | |
Electricity Demand | $34,255 | 3,567 |
kW-mo/yr
|
$9.60 | |
Electricity Fees | $31,483 | - |
|
- | |
Natural Gas | $10,687 | 734 |
MMBtu
|
$14.56 | |
Waste Disposal Costs | |||||
Water Usage | $36,334 | 1,892 |
Tgal
|
$19.20 | |
TOTAL YEARLY COSTS | $236,982 | ||||
RECOMMENDED SAVINGS* | $298,328 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $15,231 | $50 | - | - | - | - | $15,231 | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,295 | $100 |
$2,874
31,937
kWh
|
$421
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $24,855 | $7,000 |
$22,849
253,880
kWh
|
$2,006
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4321: Upgrade obsolete equipment | $66,584 | $25,000 |
$(-524.0)
(-5,824)
kWh
|
$(-92.0)
-
kW-mo/yr
|
- | - | - | $67,200 | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,274 | $2,000 |
$2,856
31,736
kWh
|
$418
-
kW-mo/yr
|
- | - | - | - | |
06 | 3.4111: Use closed cycle process to minimize waste water production | $98,974 | $65,000 |
$(-7,250.0)
(-80,559)
kWh
|
$(-1,274.0)
-
kW-mo/yr
|
- |
$27,498
-
Tgal
|
$80,000 | - | |
07 | 2.1331: Burn a less expensive grade of fuel | $2,581 | $4,000 | - | - |
$2,581
-
MMBtu
|
- | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $808 | $1,500 |
$698
7,758
kWh
|
$110
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,397 | $22,164 |
$6,791
75,453
kWh
|
$1,606
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.9114: Use solar heat to make electricty | $39,348 | $166,600 |
$28,940
321,559
kWh
|
$457
-
kW-mo/yr
|
- | - | $9,951 | - | |
11 | 2.7232: Replace existing hvac unit with high efficiency model | $32,291 | $137,607 |
$19,671
218,576
kWh
|
$2,341
-
kW-mo/yr
|
$10,279
-
MMBtu
|
- | - | - | |
12 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,690 | $12,500 |
$2,346
26,068
kWh
|
$344
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $298,328 | $443,521 |
$79,251
880,584
kWh
|
$6,337
-
kW-mo/yr
|
$12,860
-
MMBtu
|
$27,498
-
Tgal
|
$105,182 | $67,200 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | One-time Revenue or Avoided Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs