ITAC Assessment: LE0599
ITAC logo
ITAC Assessment: LE0599
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Gaskets, seals, and vibration isolators
NAICS 326291: Rubber Product Manufacturing for Mechanical Use
SIC 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 60,000
ft2
Annual Production 12,500,000
pieces
Production Hrs. Annual 7,280
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $124,223 1,387,834
kWh
Electricity Demand $34,255 3,567
kW-mo/yr
Electricity Fees $31,483 -
Natural Gas $10,687 734
MMBtu
Waste Disposal Costs
Water Usage $36,334 1,892
Tgal
TOTAL YEARLY COSTS $236,982
RECOMMENDED SAVINGS* $298,328 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings One-time Revenue or Avoided Cost Savings Increase in Production Savings
01 2.8114: Change rate schedules or other changes in utility service $15,231 $50 - - - - $15,231 -
02 2.4231: Reduce the pressure of compressed air to the minimum required $3,295 $100 $2,874
31,937
kWh
$421
-
kW-mo/yr
- - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $24,855 $7,000 $22,849
253,880
kWh
$2,006
-
kW-mo/yr
- - - -
04 2.4321: Upgrade obsolete equipment $66,584 $25,000 $(-524.0)
(-5,824)
kWh
$(-92.0)
-
kW-mo/yr
- - - $67,200
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,274 $2,000 $2,856
31,736
kWh
$418
-
kW-mo/yr
- - - -
06 3.4111: Use closed cycle process to minimize waste water production $98,974 $65,000 $(-7,250.0)
(-80,559)
kWh
$(-1,274.0)
-
kW-mo/yr
- $27,498
-
Tgal
$80,000 -
07 2.1331: Burn a less expensive grade of fuel $2,581 $4,000 - - $2,581
-
MMBtu
- - -
08 2.4221: Install compressor air intakes in coolest locations $808 $1,500 $698
7,758
kWh
$110
-
kW-mo/yr
- - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $8,397 $22,164 $6,791
75,453
kWh
$1,606
-
kW-mo/yr
- - - -
10 2.9114: Use solar heat to make electricty $39,348 $166,600 $28,940
321,559
kWh
$457
-
kW-mo/yr
- - $9,951 -
11 2.7232: Replace existing hvac unit with high efficiency model $32,291 $137,607 $19,671
218,576
kWh
$2,341
-
kW-mo/yr
$10,279
-
MMBtu
- - -
12 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,690 $12,500 $2,346
26,068
kWh
$344
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $298,328 $443,521 $79,251
880,584
kWh
$6,337
-
kW-mo/yr
$12,860
-
MMBtu
$27,498
-
Tgal
$105,182 $67,200
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings One-time Revenue or Avoided Cost Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs