| Assessment Year | 2025 |
|---|---|
| Principal Product | Foam Molding |
| NAICS | 326150: Urethane and Other Foam Product (except Polystyrene) Manufacturing |
| SIC | 3086: Plastics Foam Products |
| Sales Range | $5 M to 10M |
| # of Employees | 100 |
| Plant Area |
65,000
ft2
|
| Annual Production | 70,000
pieces
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $68,764 | 1,126,509 |
kWh
|
$0.061 |
| Electricity Demand | $16,085 | 4,081 |
kW-mo/yr
|
$3.94 |
| Electricity Fees | $12,544 | - |
|
- |
| Natural Gas | $25,288 | 2,779 |
MMBtu
|
$9.10 |
| TOTAL YEARLY COSTS | $122,681 | |||
| RECOMMENDED SAVINGS* | $47,755 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $27,684 | - |
$15,035
246,480
kWh
|
- |
$12,649
-
MMBtu
|
|
| 02 | 2.7135: Install occupancy sensors | $482 | $140 |
$482
7,904
kWh
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,438 | $3,216 |
$1,776
29,120
kWh
|
$662
-
kW-mo/yr
|
- | |
| 04 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $2,399 | $4,500 |
$(-47.0)
(-776)
kWh
|
$(-18.0)
-
kW-mo/yr
|
$2,464
-
MMBtu
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,916 | $5,984 |
$1,396
22,880
kWh
|
$520
-
kW-mo/yr
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $90 | $298 |
$66
1,075
kWh
|
$24
-
kW-mo/yr
|
- | |
| 07 | 2.7232: Replace existing hvac unit with high efficiency model | $12,746 | $62,882 |
$11,889
194,904
kWh
|
$857
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $47,755 | $77,020 |
$30,597
501,587
kWh
|
$2,045
-
kW-mo/yr
|
$15,113
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs