ITAC Assessment: LE0591
ITAC logo
ITAC Assessment: LE0591
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Foam Molding
NAICS 326150: Urethane and Other Foam Product (except Polystyrene) Manufacturing
SIC 3086: Plastics Foam Products
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area 65,000
ft2
Annual Production 70,000
pieces
Production Hrs. Annual 2,600
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,764 1,126,509
kWh
Electricity Demand $16,085 4,081
kW-mo/yr
Electricity Fees $12,544 -
Natural Gas $25,288 2,779
MMBtu
TOTAL YEARLY COSTS $122,681
RECOMMENDED SAVINGS* $47,755 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $27,684 - $15,035
246,480
kWh
- $12,649
-
MMBtu
02 2.7135: Install occupancy sensors $482 $140 $482
7,904
kWh
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,438 $3,216 $1,776
29,120
kWh
$662
-
kW-mo/yr
-
04 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $2,399 $4,500 $(-47.0)
(-776)
kWh
$(-18.0)
-
kW-mo/yr
$2,464
-
MMBtu
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,916 $5,984 $1,396
22,880
kWh
$520
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $90 $298 $66
1,075
kWh
$24
-
kW-mo/yr
-
07 2.7232: Replace existing hvac unit with high efficiency model $12,746 $62,882 $11,889
194,904
kWh
$857
-
kW-mo/yr
-
TOTAL RECOMMENDED $47,755 $77,020 $30,597
501,587
kWh
$2,045
-
kW-mo/yr
$15,113
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs