Assessment Year | 2024 |
---|---|
Principal Product | Metal Stampings |
NAICS | 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive) |
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 146 |
Plant Area |
149,903
ft2
|
Annual Production | 115,207
units
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $329,984 | 4,300,148 |
kWh
|
$0.077 |
Electricity Demand | $39,787 | 11,206 |
kW-mo/yr
|
$3.55 |
Electricity Fees | $44,365 | - |
|
- |
Natural Gas | $43,991 | 3,290 |
MMBtu
|
$13.37 |
TOTAL YEARLY COSTS | $458,127 | |||
RECOMMENDED SAVINGS* | $49,054 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $1,582 | $70 |
$1,582
20,550
kWh
|
- | - | |
02 | 2.7261: Install timers and/or thermostats | $17,326 | $1,600 |
$8,114
105,374
kWh
|
- |
$9,212
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,379 | $2,500 |
$6,379
82,811
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,427 | $35,960 |
$14,414
187,200
kWh
|
$13
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,340 | $49,500 |
$8,783
114,049
kWh
|
$557
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $49,054 | $89,630 |
$39,272
509,984
kWh
|
$570
-
kW-mo/yr
|
$9,212
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs