ITAC Assessment: LE0586
ITAC logo
ITAC Assessment: LE0586
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Metal Stampings
NAICS 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive)
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 146
Plant Area 149,903
ft2
Annual Production 115,207
units
Production Hrs. Annual 4,160
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $329,984 4,300,148
kWh
Electricity Demand $39,787 11,206
kW-mo/yr
Electricity Fees $44,365 -
Natural Gas $43,991 3,290
MMBtu
TOTAL YEARLY COSTS $458,127
RECOMMENDED SAVINGS* $49,054 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7135: Install occupancy sensors $1,582 $70 $1,582
20,550
kWh
- -
02 2.7261: Install timers and/or thermostats $17,326 $1,600 $8,114
105,374
kWh
- $9,212
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,379 $2,500 $6,379
82,811
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $14,427 $35,960 $14,414
187,200
kWh
$13
-
kW-mo/yr
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,340 $49,500 $8,783
114,049
kWh
$557
-
kW-mo/yr
-
TOTAL RECOMMENDED $49,054 $89,630 $39,272
509,984
kWh
$570
-
kW-mo/yr
$9,212
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs