Assessment Year | 2024 |
---|---|
Principal Product | Carbon and Graphite Product |
NAICS | 335991: Carbon and Graphite Product Manufacturing |
SIC | 3624: Carbon and Graphite Products |
Sales Range | $100 M to 500M |
# of Employees | 125 |
Plant Area |
55,000
ft2
|
Annual Production | 20,000,000
pieces
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $81,723 | 916,790 |
kWh
|
$0.089 |
Electricity Demand | $20,727 | 2,717 |
kW-mo/yr
|
$7.63 |
Electricity Fees | $22,150 | - |
|
- |
Natural Gas | $29,070 | 3,071 |
MMBtu
|
$9.47 |
TOTAL YEARLY COSTS | $153,670 | |||
RECOMMENDED SAVINGS* | $40,387 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,016 | - |
$393
4,420
kWh
|
$623
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,789 | $100 |
$1,467
16,487
kWh
|
$322
-
kW-mo/yr
|
- | |
03 | 2.7261: Install timers and/or thermostats | $5,156 | $200 | - | - |
$5,156
-
MMBtu
|
|
04 | 2.7261: Install timers and/or thermostats | $3,800 | $400 |
$2,806
31,523
kWh
|
- |
$994
-
MMBtu
|
|
05 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $10,054 | $5,500 |
$(-230.0)
(-2,560)
kWh
|
$(-107.0)
-
kW-mo/yr
|
$10,391
-
MMBtu
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $357 | $1,080 |
$250
2,802
kWh
|
$107
-
kW-mo/yr
|
- | |
07 | 2.2443: Re-use or recycle hot or cold process exhaust air | $1,314 | $4,000 | - | - |
$1,314
-
MMBtu
|
|
08 | 2.7232: Replace existing hvac unit with high efficiency model | $1,023 | $4,500 |
$168
1,888
kWh
|
$855
-
kW-mo/yr
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,861 | $13,312 |
$2,319
26,060
kWh
|
$542
-
kW-mo/yr
|
- | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $697 | $3,400 |
$582
6,548
kWh
|
$115
-
kW-mo/yr
|
- | |
11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,320 | $61,333 |
$10,285
115,559
kWh
|
$2,035
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $40,387 | $93,825 |
$18,040
202,727
kWh
|
$4,492
-
kW-mo/yr
|
$17,855
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs