Assessment Year | 2023 |
---|---|
Principal Product | Chemical Processing |
NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
70,000
ft2
|
Annual Production | 800,000
lb
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $433,811 | 8,168,400 |
kWh
|
$0.053 |
Electricity Demand | $69,492 | 27,284 |
kW-mo/yr
|
$2.55 |
Electricity Fees | $6,004 | - |
|
- |
TOTAL YEARLY COSTS | $509,307 | |||
RECOMMENDED SAVINGS* | $56,399 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,184 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,946 | $100 |
$3,821
72,100
kWh
|
$1,125
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,153 | $11,000 |
$10,983
207,222
kWh
|
$3,170
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,870 | $2,400 |
$1,452
27,413
kWh
|
$418
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,184 | $4,100 |
$2,756
52,000
kWh
|
$428
-
kW-mo/yr
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,260 | $9,128 |
$5,209
98,296
kWh
|
$1,051
-
kW-mo/yr
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $986 | $2,000 |
$591
11,147
kWh
|
$395
-
kW-mo/yr
|
- | |
07 | 2.2437: Recover waste heat from equipment | $25,000 | $120,000 | - | - | $25,000 | |
TOTAL RECOMMENDED | $56,399 | $148,728 |
$24,812
468,178
kWh
|
$6,587
-
kW-mo/yr
|
$25,000 | ||
TOTAL IMPLEMENTED | $3,184 | $4,100 |
$2,756
52,000
kWh
|
$428
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs