Assessment Year | 2022 |
---|---|
Principal Product | Cans |
NAICS | 332431: Metal Can Manufacturing |
SIC | 3411: Metal Cans |
Sales Range | $100 M to 500M |
# of Employees | 84 |
Plant Area |
265,000
ft2
|
Annual Production | 1,000,000,000
units
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,178,010 | 19,009,361 |
kWh
|
$0.062 |
Electricity Demand | $147,730 | 26,907 |
kW-mo/yr
|
$5.49 |
Electricity Fees | $109,988 | - |
|
- |
Natural Gas | $744,589 | 162,650 |
MMBtu
|
$4.58 |
TOTAL YEARLY COSTS | $2,180,317 | |||
RECOMMENDED SAVINGS* | $189,139 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $75,114 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,198 | $2,600 |
$5,649
91,100
kWh
|
$549
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $6,190 | $4,000 |
$5,533
89,241
kWh
|
$657
-
kW-mo/yr
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,790 | $8,800 |
$6,027
101,206
kWh
|
$763
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,077 | $30,000 |
$8,984
144,908
kWh
|
$1,093
-
kW-mo/yr
|
- | |
05 | 2.4226: Use / purchase optimum sized compressor | $45,859 | $175,000 |
$42,263
681,656
kWh
|
$3,596
-
kW-mo/yr
|
- | |
06 | 2.2441: Preheat boiler makeup water with waste process heat | $114,025 | $450,000 |
$(-6,122.0)
(-97,755)
kWh
|
- |
$120,147
-
MMBtu
|
|
TOTAL RECOMMENDED | $189,139 | $670,400 |
$62,334
1,010,356
kWh
|
$6,658
-
kW-mo/yr
|
$120,147
-
MMBtu
|
||
TOTAL IMPLEMENTED | $75,114 | $220,400 |
$68,456
1,108,111
kWh
|
$6,658
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs