ITAC Assessment: OR0185
ITAC logo
ITAC Assessment: OR0185
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Laminated Joists
NAICS
n/a
SIC 2439: Structural Wood Members, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 30,000
ft2
Annual Production 73,000,000
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $647,086 24,021,102
kWh
Natural Gas $598,068 160,094
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,790 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Personnel Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $338 - $338
9,379
kWh
-
02 2.7134: Use photocell controls $821 $209 $544
28,136
kWh
$277
03 2.3212: Optimize plant power factor $7,883 $6,600 $7,883
-
kWh
-
04 2.6218: Turn off equipment when not in use $3,782 $4,446 $3,782
195,193
kWh
-
05 2.4133: Use most efficient type of electric motors $2,597 $7,329 $2,597
93,494
kWh
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,369 $11,250 $2,369
88,218
kWh
-
TOTAL RECOMMENDED $17,790 $29,834 $17,513
414,420
kWh
$277
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs