Assessment Year | 2021 |
---|---|
Principal Product | Flexible Packaging |
NAICS | 326112: Plastics Packaging Film and Sheet (including Laminated) Manufacturing |
SIC | 2671: Packaging Paper and Plastics Film, Coated and Laminated |
Sales Range | $50 M to 100M |
# of Employees | 255 |
Plant Area |
65,000
ft2
|
Annual Production | 20,000,000
units
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $182,201 | 6,210,044 |
kWh
|
$0.029 |
Electricity Demand | $56,484 | 11,551 |
kW-mo/yr
|
$4.89 |
Electricity Fees | $64,955 | - |
|
- |
Natural Gas | $139,881 | 32,033 |
MMBtu
|
$4.37 |
TOTAL YEARLY COSTS | $443,521 | |||
RECOMMENDED SAVINGS* | $34,912 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,635 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,511 | $200 |
$1,227
42,172
kWh
|
$284
-
kW-mo/yr
|
|
02 | 2.4221: Install compressor air intakes in coolest locations | $1,124 | $1,200 |
$1,104
37,067
kWh
|
$20
-
kW-mo/yr
|
|
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,984 | $30,000 |
$14,700
506,882
kWh
|
$284
-
kW-mo/yr
|
|
04 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $8,448 | $25,000 |
$6,859
236,511
kWh
|
$1,589
-
kW-mo/yr
|
|
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,118 | $11,000 |
$2,556
88,153
kWh
|
$562
-
kW-mo/yr
|
|
06 | 2.7232: Replace existing hvac unit with high efficiency model | $5,727 | $36,000 |
$4,646
160,197
kWh
|
$1,081
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $34,912 | $103,400 |
$31,092
1,070,982
kWh
|
$3,820
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $2,635 | $1,400 |
$2,331
79,239
kWh
|
$304
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs