ITAC Assessment: LE0511
ITAC logo
ITAC Assessment: LE0511
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Lumber
NAICS 321911: Wood Window and Door Manufacturing
SIC 2431: Millwork
Sales Range $50
M
to 100
M
# of Employees 39
Plant Area 150,000
ft2
Annual Production 100,000
units
Production Hrs. Annual 5,720
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,476 995,099
kWh
Electricity Demand $17,989 4,482
kW-mo/yr
Electricity Fees $15,312 -
Natural Gas $26,629 7,783
MMBtu
Fuel Oil #2 $8,321 603
MMBtu
Other Energy $3,962 235
MMBtu
TOTAL YEARLY COSTS $117,689
RECOMMENDED SAVINGS* $16,937 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,197

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Other Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $824 $35 $672
14,619
kWh
$152
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,197 $14,875 $5,152
111,997
kWh
$1,045
-
kW-mo/yr
- -
03 2.2437: Recover waste heat from equipment $2,917 $8,000 - - $2,917
-
MMBtu
-
04 2.7233: Use properly designed and sized hvac equipment $2,375 $7,600 - - $2,375
-
MMBtu
-
05 2.4221: Install compressor air intakes in coolest locations $289 $1,000 $245
5,317
kWh
$44
-
kW-mo/yr
- -
06 2.4226: Use / purchase optimum sized compressor $3,092 $12,000 $2,593
56,365
kWh
$499
-
kW-mo/yr
- -
07 2.1332: Convert combustion equipment to burn natural gas $1,243 $6,000 - - $827
-
MMBtu
$416
-
MMBtu
TOTAL RECOMMENDED $16,937 $49,510 $8,662
188,298
kWh
$1,740
-
kW-mo/yr
$6,119
-
MMBtu
$416
-
MMBtu
TOTAL IMPLEMENTED $6,197 $14,875 $5,152
111,997
kWh
$1,045
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Other Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs