ITAC Assessment: LE0486
ITAC logo
ITAC Assessment: LE0486
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Power Transmission Components
NAICS 333613: Mechanical Power Transmission Equipment Manufacturing
SIC 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 50
Plant Area 450,000
ft2
Annual Production 11,000
units
Production Hrs. Annual 2,912
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,459,312 24,493,080
kWh
Electricity Demand $318,464 44,831
kW-mo/yr
Electricity Fees $30,314 -
Natural Gas $339,106 61,973
MMBtu
TOTAL YEARLY COSTS $2,147,196
RECOMMENDED SAVINGS* $127,704 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,496

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $57,024 $500 $57,024
950,404
kWh
- -
02 2.7261: Install timers and/or thermostats $8,764 $720 $8,764
146,400
kWh
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,174 $1,540 $1,010
16,831
kWh
$164
-
kW-mo/yr
-
04 2.7233: Use properly designed and sized hvac equipment $15,202 $21,000 - - $15,202
-
MMBtu
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $35,256 $65,000 $26,612
460,204
kWh
$8,644
-
kW-mo/yr
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,726 $7,400 $3,726
62,103
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $6,558 $28,275 $5,273
88,884
kWh
$1,285
-
kW-mo/yr
-
TOTAL RECOMMENDED $127,704 $124,435 $102,409
1,724,826
kWh
$10,093
-
kW-mo/yr
$15,202
-
MMBtu
TOTAL IMPLEMENTED $16,496 $30,535 $15,047
252,115
kWh
$1,449
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs