ITAC Assessment: SF0229
ITAC logo
ITAC Assessment: SF0229
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Gas and Chemical Systems
NAICS
n/a
SIC 3621: Motors and Generators
Sales Range $10
M
to 50
M
# of Employees 131
Plant Area 45,000
ft2
Annual Production 300,000
units
Production Hrs. Annual 4,680
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $136,132 985,753
kWh
Electricity Demand $15,483 193
kW-mo/yr
Natural Gas $6,848 486
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,510 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Other Liquid (non-haz) Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $3,292 $2,320 $3,292
23,836
kWh
-
02 3.5217: Reuse / recycle/ sell paper products $1,000 - - $1,000
-
gal
03 3.6193: Install equipment (eg compactor) to reduce disposal costs $9,218 $15,374 - $9,218
-
gal
TOTAL RECOMMENDED $13,510 $17,694 $3,292
23,836
kWh
$10,218
-
gal
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs