| Assessment Year | 2019 |
|---|---|
| Principal Product | Calcium Carbonate |
| NAICS | 325180: Other Basic Inorganic Chemical Manufacturing |
| SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 42 |
| Plant Area |
1,500,000
ft2
|
| Annual Production | 120,000
ton
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Maryland |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,522,673 | 25,480,148 |
kWh
|
$0.060 |
| Electricity Demand | $140,767 | 50,095 |
kW-mo/yr
|
$2.81 |
| Electricity Fees | $478,235 | - |
|
- |
| Natural Gas | $588,000 | 113,818 |
MMBtu
|
$5.17 |
| TOTAL YEARLY COSTS | $2,729,675 | |||
| RECOMMENDED SAVINGS* | $241,036 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6212: Turn off equipment during breaks, reduce operating time | $6,517 | $120 |
$6,517
108,617
kWh
|
- | - | - | |
| 02 | 2.4322: Use or replace with energy efficient substitutes | $22,930 | $7,500 |
$21,514
358,570
kWh
|
$1,416
-
kW-mo/yr
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,180 | $2,250 |
$4,855
80,920
kWh
|
$325
-
kW-mo/yr
|
- | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $9,784 | $9,200 |
$9,784
163,061
kWh
|
- | - | - | |
| 05 | 2.1224: Replace boiler | $162,332 | $344,000 | - | - |
$42,332
-
MMBtu
|
$120,000 | |
| 06 | 2.4226: Use / purchase optimum sized compressor | $28,883 | $60,000 |
$27,416
456,925
kWh
|
$1,467
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,410 | $17,950 |
$5,070
84,504
kWh
|
$340
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $241,036 | $441,020 |
$75,156
1,252,597
kWh
|
$3,548
-
kW-mo/yr
|
$42,332
-
MMBtu
|
$120,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs