Assessment Year | 2019 |
---|---|
Principal Product | Plastics |
NAICS | 326113: Unlaminated Plastics Film and Sheet (except Packaging) Manufacturing |
SIC | 3081: Unsupported Plastics Film and Sheet |
Sales Range | $50 M to 100M |
# of Employees | 20 |
Plant Area |
90,000
ft2
|
Annual Production | 70,000,000
units
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,577,115 | 22,635,727 |
kWh
|
$0.070 |
Electricity Demand | $515,042 | 36,590 |
kW-mo/yr
|
$14.08 |
Electricity Fees | $54,869 | - |
|
- |
Natural Gas | $19,014 | 1,947 |
MMBtu
|
$9.77 |
TOTAL YEARLY COSTS | $2,166,040 | |||
RECOMMENDED SAVINGS* | $66,230 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $58,361 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $666 | $35 |
$168
2,400
kWh
|
- |
$498
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,203 | $2,000 |
$5,359
76,552
kWh
|
$1,844
-
kW-mo/yr
|
- | |
03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $24,476 | $20,000 |
$20,041
286,303
kWh
|
$4,435
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $26,397 | $30,000 |
$20,681
295,440
kWh
|
$5,716
-
kW-mo/yr
|
- | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $6,634 | $18,400 |
$5,198
74,256
kWh
|
$1,436
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $854 | $3,225 |
$530
7,568
kWh
|
$324
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $66,230 | $73,660 |
$51,977
742,519
kWh
|
$13,755
-
kW-mo/yr
|
$498
-
MMBtu
|
||
TOTAL IMPLEMENTED | $58,361 | $71,625 |
$46,450
663,567
kWh
|
$11,911
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs