| Assessment Year | 1999 |
|---|---|
| Principal Product | Aluminum extrusions |
| NAICS |
n/a
|
| SIC | 3356: Rolling, Drawing, and Extruding of Nonferrous Metals, Except Copper and Aluminum |
| Sales Range | $10 M to 50M |
| # of Employees | 45 |
| Plant Area |
96,200
ft2
|
| Annual Production | 12,000,000
lb
|
| Production Hrs. Annual | 6,022
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $93,647 | 2,730,950 |
kWh
|
$0.034 |
| Electricity Demand | $68,107 | 9,606 |
kW-mo/yr
|
$7.09 |
| Natural Gas | $13,685 | 2,831 |
MMBtu
|
$4.83 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $253,431 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $133,383 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,689 | $3,628 |
$1,877
55,100
kWh
|
$812
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $272 | $1,750 |
$221
2,931
kWh
|
$51
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,374 | $50 |
$1,080
23,154
kWh
|
$294
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,246 | $450 |
$981
21,102
kWh
|
$265
-
kW-mo/yr
|
- | - | - | |
| 05 | 3.4111: Use closed cycle process to minimize waste water production | $9,048 | $5,000 |
$(-5,105.0)
(-150,059)
kWh
|
$(-4,333.0)
-
kW-mo/yr
|
- | - |
$18,486
-
Tgal
|
|
| 06 | 3.1192: Reduce scrap production | $120,000 | $80,000 | - | - |
$120,000
-
lb
|
- | - | |
| 07 | 4.513: Re-arrange equipment layout to reduce labor costs | $118,802 | $300 | - | - | - | $118,802 | - | |
| TOTAL RECOMMENDED | $253,431 | $91,178 |
$(-946.0)
(-47,772)
kWh
|
$(-2,911.0)
-
kW-mo/yr
|
$120,000
-
lb
|
$118,802 |
$18,486
-
Tgal
|
||
| TOTAL IMPLEMENTED | $133,383 | $90,428 |
$(-1,927.0)
(-68,874)
kWh
|
$(-3,176.0)
-
kW-mo/yr
|
$120,000
-
lb
|
- |
$18,486
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs