Assessment Year | 2018 |
---|---|
Principal Product | PTFE & Waxes |
NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 53 |
Plant Area |
114,200
ft2
|
Annual Production | 500,000
units
|
Production Hrs. Annual | 5,610
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $510,915 | 4,564,575 |
kWh
|
$0.11 |
Electricity Demand | $114,448 | 16,834 |
kW-mo/yr
|
$6.80 |
Electricity Fees | $48,982 | - |
|
- |
Natural Gas | $82,985 | 8,467 |
MMBtu
|
$9.80 |
TOTAL YEARLY COSTS | $757,330 | |||
RECOMMENDED SAVINGS* | $32,791 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,590 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $10,236 | $500 |
$9,148
81,678
kWh
|
$1,088
-
kW-mo/yr
|
- | |
02 | 2.7261: Install timers and/or thermostats | $1,449 | $150 |
$332
2,966
kWh
|
$1,117
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,024 | $1,500 |
$8,956
79,968
kWh
|
$1,068
-
kW-mo/yr
|
- | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,764 | $1,200 | - | - |
$1,764
-
MMBtu
|
|
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $744 | $600 |
$594
5,307
kWh
|
$150
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,163 | $3,019 |
$1,959
17,491
kWh
|
$204
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,058 | $6,563 |
$3,058
27,300
kWh
|
- | - | |
08 | 2.2414: Use waste heat from hot flue gases to preheat | $3,352 | $22,000 | - | - |
$3,352
-
MMBtu
|
|
TOTAL RECOMMENDED | $32,791 | $35,532 |
$24,048
214,710
kWh
|
$3,627
-
kW-mo/yr
|
$5,116
-
MMBtu
|
||
TOTAL IMPLEMENTED | $15,590 | $9,863 |
$12,609
112,575
kWh
|
$1,218
-
kW-mo/yr
|
$1,764
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs