Assessment Year | 2018 |
---|---|
Principal Product | Plastic films |
NAICS | 326113: Unlaminated Plastics Film and Sheet (except Packaging) Manufacturing |
SIC | 3081: Unsupported Plastics Film and Sheet |
Sales Range | $10 M to 50M |
# of Employees | 84 |
Plant Area |
100,000
ft2
|
Annual Production | 25,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $505,226 | 12,232,800 |
kWh
|
$0.041 |
Electricity Demand | $57,906 | 22,735 |
kW-mo/yr
|
$2.55 |
Electricity Fees | $262,559 | - |
|
- |
Natural Gas | $61,017 | 6,725 |
MMBtu
|
$9.07 |
TOTAL YEARLY COSTS | $886,708 | |||
RECOMMENDED SAVINGS* | $80,770 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $58,689 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,723 | $1,500 |
$5,343
130,308
kWh
|
$380
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $554 | $300 |
$509
12,402
kWh
|
$46
-
kW-mo/yr
|
- | |
03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $40,361 | $48,000 |
$37,780
921,473
kWh
|
$2,581
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,821 | $20,500 |
$11,970
291,940
kWh
|
$852
-
kW-mo/yr
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,855 | $8,000 |
$4,534
110,583
kWh
|
$321
-
kW-mo/yr
|
- | |
06 | 2.7233: Use properly designed and sized hvac equipment | $9,261 | $28,000 | - | - |
$9,261
-
MMBtu
|
|
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,301 | $23,000 |
$5,786
141,120
kWh
|
$515
-
kW-mo/yr
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $895 | $4,400 |
$895
21,840
kWh
|
- | - | |
TOTAL RECOMMENDED | $80,770 | $133,700 |
$66,815
1,629,666
kWh
|
$4,695
-
kW-mo/yr
|
$9,261
-
MMBtu
|
||
TOTAL IMPLEMENTED | $58,689 | $85,200 |
$54,846
1,337,726
kWh
|
$3,843
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs