| Assessment Year | 2018 |
|---|---|
| Principal Product | Silver coated threads |
| NAICS | 313110: Fiber, Yarn, and Thread Mills |
| SIC | 2284: Thread Mills |
| Sales Range | $1 M to 5M |
| # of Employees | 31 |
| Plant Area |
65,000
ft2
|
| Annual Production | 8,000
thousand feet
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $187,445 | 4,402,100 |
kWh
|
$0.043 |
| Electricity Demand | $58,651 | 8,440 |
kW-mo/yr
|
$6.95 |
| Natural Gas | $86,098 | 14,595 |
MMBtu
|
$5.90 |
| TOTAL YEARLY COSTS | $332,194 | |||
| RECOMMENDED SAVINGS* | $50,565 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,167 | $1,000 |
$9,138
212,511
kWh
|
$2,029
-
kW-mo/yr
|
- | - | |
| 02 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $16,243 | $8,000 |
$(-3,757.0)
(-87,360)
kWh
|
- | - | $20,000 | |
| 03 | 2.4323: Use optimum size and capacity equipment | $2,802 | $3,000 |
$2,802
65,170
kWh
|
- | - | - | |
| 04 | 2.7135: Install occupancy sensors | $1,023 | $1,625 |
$1,023
23,795
kWh
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,186 | $2,470 |
$971
22,574
kWh
|
$215
-
kW-mo/yr
|
- | - | |
| 06 | 2.2441: Preheat boiler makeup water with waste process heat | $3,038 | $8,000 | - | - |
$3,038
-
MMBtu
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,643 | $36,750 |
$7,892
183,546
kWh
|
$1,751
-
kW-mo/yr
|
- | - | |
| 08 | 2.4226: Use / purchase optimum sized compressor | $5,463 | $22,000 |
$4,469
103,932
kWh
|
$994
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $50,565 | $82,845 |
$22,538
524,168
kWh
|
$4,989
-
kW-mo/yr
|
$3,038
-
MMBtu
|
$20,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs