ITAC Assessment: LE0448
ITAC logo
ITAC Assessment: LE0448
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Architectural Glazing Systems
NAICS 332321: Metal Window and Door Manufacturing
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 33
Plant Area 290,000
ft2
Annual Production 707
units
Production Hrs. Annual 3,120
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $118,746 1,554,200
kWh
Electricity Demand $25,583 6,608
kW-mo/yr
Electricity Fees $5,400 -
LPG $40,214 3,671
MMBtu
TOTAL YEARLY COSTS $189,943
RECOMMENDED SAVINGS* $45,718 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,830

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings
01 2.7261: Install timers and/or thermostats $2,899 $25 $1,912
25,160
kWh
- $986
-
MMBtu
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,450 $25 $1,372
18,058
kWh
$77
-
kW-mo/yr
-
03 2.7232: Replace existing hvac unit with high efficiency model $14,206 $20,625 $13,544
178,214
kWh
$662
-
kW-mo/yr
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,228 $19,000 $9,452
124,363
kWh
$1,776
-
kW-mo/yr
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $874 $1,500 $754
9,915
kWh
$120
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,660 $5,250 $1,660
21,840
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,721 $11,738 $2,276
29,952
kWh
$445
-
kW-mo/yr
-
08 2.2441: Preheat boiler makeup water with waste process heat $6,258 $30,000 - - $6,258
-
MMBtu
09 2.7142: Utilize higher efficiency lamps and/or ballasts $843 $4,225 $696
9,152
kWh
$147
-
kW-mo/yr
-
10 2.7261: Install timers and/or thermostats $3,580 $20,000 $1,158
15,238
kWh
- $2,422
-
MMBtu
TOTAL RECOMMENDED $45,718 $112,388 $32,824
431,892
kWh
$3,228
-
kW-mo/yr
$9,667
-
MMBtu
TOTAL IMPLEMENTED $15,830 $51,263 $7,916
104,162
kWh
$670
-
kW-mo/yr
$7,245
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs