ITAC Assessment: UK1609
ITAC logo
ITAC Assessment: UK1609
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Wood Products
NAICS 321918: Other Millwork (including Flooring)
SIC 2431: Millwork
Sales Range $10
M
to 50
M
# of Employees 400
Plant Area 875,000
ft2
Annual Production 1,000,000
units
Production Hrs. Annual 2,106
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $290,596 4,168,800
kWh
Electricity Demand $222,563 35,305
kW-mo/yr
Electricity Fees $928 -
TOTAL YEARLY COSTS $514,087
RECOMMENDED SAVINGS* $64,808 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,880

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $54,548 - $54,548
782,609
kWh
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,223 $3,000 $9,223
132,328
kWh
-
03 2.2123: Insulate feedwater tank $380 $140 $336
4,817
kWh
$44
-
kW-mo/yr
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $657 - $657
9,426
kWh
-
TOTAL RECOMMENDED $64,808 $3,140 $64,764
929,180
kWh
$44
-
kW-mo/yr
TOTAL IMPLEMENTED $9,880 $3,000 $9,880
141,754
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs