| Assessment Year | 2017 |
|---|---|
| Principal Product | Metallic components, Power coating |
| NAICS | 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
| SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 92 |
| Plant Area |
42,150
ft2
|
| Annual Production | 2,000,000
pieces
|
| Production Hrs. Annual | 2,470
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $103,753 | 1,649,104 |
kWh
|
$0.063 |
| Electricity Demand | $16,729 | 6,568 |
kW-mo/yr
|
$2.55 |
| Electricity Fees | $10,331 | - |
|
- |
| Natural Gas | $113,882 | 20,575 |
MMBtu
|
$5.53 |
| TOTAL YEARLY COSTS | $244,695 | |||
| RECOMMENDED SAVINGS* | $22,126 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,963 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,107 | $1,000 |
$5,785
91,827
kWh
|
$322
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,590 | $1,500 |
$765
12,140
kWh
|
$3,825
-
kW-mo/yr
|
- | |
| 03 | 2.2441: Preheat boiler makeup water with waste process heat | $9,163 | $3,000 | - | - |
$9,163
-
MMBtu
|
|
| 04 | 2.4221: Install compressor air intakes in coolest locations | $525 | $750 |
$494
7,845
kWh
|
$31
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,741 | $6,692 |
$1,455
23,094
kWh
|
$286
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $22,126 | $12,942 |
$8,499
134,906
kWh
|
$4,464
-
kW-mo/yr
|
$9,163
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $12,963 | $9,942 |
$8,499
134,906
kWh
|
$4,464
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs