ITAC Assessment: LE0430
ITAC logo
ITAC Assessment: LE0430
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Cast Products
NAICS 331513: Steel Foundries (except Investment)
SIC 3325: Steel Foundries, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 32
Plant Area 60,000
ft2
Annual Production 246
ton
Production Hrs. Annual 2,600
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $145,349 2,543,552
kWh
Electricity Demand $38,001 12,060
kW-mo/yr
Electricity Fees $21,963 -
Natural Gas $79,243 7,190
MMBtu
TOTAL YEARLY COSTS $284,556
RECOMMENDED SAVINGS* $21,440 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,637

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,483 $55 $2,215
38,864
kWh
$268
-
kW-mo/yr
-
02 2.7261: Install timers and/or thermostats $764 $55 $169
2,966
kWh
- $595
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,280 $1,000 $3,006
52,744
kWh
$274
-
kW-mo/yr
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $402 $300 $311
5,450
kWh
$91
-
kW-mo/yr
-
05 2.7232: Replace existing hvac unit with high efficiency model $3,320 $8,550 $3,043
53,387
kWh
$277
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,407 $15,961 $3,909
68,578
kWh
$498
-
kW-mo/yr
-
07 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $2,616 $10,500 $(-156.0)
(-2,746)
kWh
$(-126.0)
-
kW-mo/yr
$2,898
-
MMBtu
08 2.7142: Utilize higher efficiency lamps and/or ballasts $3,523 $18,585 $2,672
46,883
kWh
$851
-
kW-mo/yr
-
09 2.7142: Utilize higher efficiency lamps and/or ballasts $645 $3,413 $560
9,828
kWh
$85
-
kW-mo/yr
-
TOTAL RECOMMENDED $21,440 $58,419 $15,729
275,954
kWh
$2,218
-
kW-mo/yr
$3,493
-
MMBtu
TOTAL IMPLEMENTED $15,637 $49,814 $10,471
183,703
kWh
$1,673
-
kW-mo/yr
$3,493
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings