ITAC Assessment: LE0428
ITAC logo
ITAC Assessment: LE0428
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Bronze Casting
NAICS 331529: Other Nonferrous Metal Foundries (except Die-Casting)
SIC 3369: Nonferrous Foundries, Except Aluminum and Copper
Sales Range $10
M
to 50
M
# of Employees 49
Plant Area 44,000
ft2
Annual Production 2,000
units
Production Hrs. Annual 2,450
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $200,814 2,533,108
kWh
Electricity Demand $116,286 20,322
kW-mo/yr
Electricity Fees $41,650 -
Natural Gas $26,480 2,672
MMBtu
TOTAL YEARLY COSTS $385,230
RECOMMENDED SAVINGS* $11,966 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,673

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,923 $1,000 $1,208
15,296
kWh
$715
-
kW-mo/yr
-
02 2.4221: Install compressor air intakes in coolest locations $340 $800 $214
2,713
kWh
$126
-
kW-mo/yr
-
03 2.4226: Use / purchase optimum sized compressor $3,953 $9,500 $2,797
35,409
kWh
$1,155
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,863 $10,608 $2,114
26,754
kWh
$749
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $769 $3,192 $569
7,203
kWh
$200
-
kW-mo/yr
-
06 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $2,118 $10,500 $(-338.9)
(-4,290)
kWh
$(-228.8)
-
kW-mo/yr
$2,686
-
MMBtu
TOTAL RECOMMENDED $11,966 $35,600 $6,563
83,085
kWh
$2,717
-
kW-mo/yr
$2,686
-
MMBtu
TOTAL IMPLEMENTED $7,673 $25,300 $3,552
44,963
kWh
$1,436
-
kW-mo/yr
$2,686
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs