Assessment Year | 2016 |
---|---|
Principal Product | wire rope |
NAICS | 332618: Other Fabricated Wire Product Manufacturing |
SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
Sales Range | $100 M to 500M |
# of Employees | 140 |
Plant Area |
186,600
ft2
|
Annual Production | 30,751
ton
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $363,708 | 6,327,900 |
kWh
|
$0.057 |
Electricity Demand | $29,210 | 13,733 |
kW-mo/yr
|
$2.13 |
Electricity Fees | $16,824 | - |
|
- |
Natural Gas | $33,763 | 4,923 |
MMBtu
|
$6.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,559 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,940 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $5,124 | $500 | - | - |
$5,124
-
MMBtu
|
|
02 | 2.7135: Install occupancy sensors | $1,494 | $725 |
$1,494
26,208
kWh
|
- | - | |
03 | 2.2437: Recover waste heat from equipment | $3,060 | $1,800 | - | - |
$3,060
-
MMBtu
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $973 | $1,000 |
$865
15,173
kWh
|
$109
-
kW-mo/yr
|
- | |
05 | 2.7261: Install timers and/or thermostats | $482 | $590 |
$66
1,158
kWh
|
- |
$416
-
MMBtu
|
|
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,404 | $15,000 |
$8,085
141,842
kWh
|
$320
-
kW-mo/yr
|
- | |
07 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $13,462 | $25,000 |
$12,025
210,960
kWh
|
$1,438
-
kW-mo/yr
|
- | |
08 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $5,559 | $14,000 |
$8,670
152,100
kWh
|
$848
-
kW-mo/yr
|
$(-3,958.2)
-
MMBtu
|
|
TOTAL RECOMMENDED | $38,559 | $58,615 |
$31,204
547,441
kWh
|
$2,714
-
kW-mo/yr
|
$4,641
-
MMBtu
|
||
TOTAL IMPLEMENTED | $29,940 | $42,815 |
$22,534
395,341
kWh
|
$1,866
-
kW-mo/yr
|
$5,540
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs