ITAC Assessment: LE0412
ITAC logo
ITAC Assessment: LE0412
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Remanufactured Engines
NAICS 333618: Other Engine Equipment Manufacturing
SIC 3519: Internal Combustion Engines, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 175
Plant Area 70,000
ft2
Annual Production 5,000
pieces
Production Hrs. Annual 6,552
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $206,567 2,796,600
kWh
Electricity Demand $36,389 8,680
kW-mo/yr
Electricity Fees $22,005 -
Natural Gas $76,475 9,275
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $40,522 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,486

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2442: Preheat combustion air with waste heat $13,984 $20,000 - - $13,984
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,397 $8,050 $2,770
37,434
kWh
$2,627
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,688 $19,250 $5,452
73,678
kWh
$1,236
-
kW-mo/yr
-
04 2.2136: Install / repair insulation on steam lines $462 $1,382 - - $462
-
MMBtu
05 2.4226: Use / purchase optimum sized compressor $4,944 $18,280 $4,533
61,260
kWh
$411
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,108 $4,125 $957
12,929
kWh
$151
-
kW-mo/yr
-
07 2.7243: Improve air circulation with destratification fans / other methods $7,939 $35,720 $6,690
90,410
kWh
$1,249
-
kW-mo/yr
-
TOTAL RECOMMENDED $40,522 $106,807 $20,403
275,711
kWh
$5,673
-
kW-mo/yr
$14,446
-
MMBtu
TOTAL IMPLEMENTED $20,486 $64,402 $14,913
201,522
kWh
$5,112
-
kW-mo/yr
$462
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs