| Assessment Year | 1995 |
|---|---|
| Principal Product | Design and manufacturing of electronic equipment |
| NAICS |
n/a
|
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $10 M to 50M |
| # of Employees | 213 |
| Plant Area |
108,000
ft2
|
| Annual Production | 10
pieces
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $66,441 | 1,873,681 |
kWh
|
$0.035 |
| Natural Gas | $7,419 | 1,455 |
MMBtu
|
$5.10 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,127 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,351 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7226: Use computer programs to optimize hvac performance | $7,900 | $25,000 |
$4,044
-
kWh
|
$3,856
-
MMBtu
|
|
| 02 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,638 | - |
$1,638
11,137
kWh
|
- | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $913 | $128 |
$913
13,189
kWh
|
- | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $903 | - |
$903
-
kWh
|
- | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $837 | $540 |
$837
23,447
kWh
|
- | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $749 | $112 |
$749
10,844
kWh
|
- | |
| 07 | 2.7135: Install occupancy sensors | $467 | $1,100 |
$467
13,189
kWh
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $387 | $684 |
$387
8,206
kWh
|
- | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $333 | $1,186 |
$333
7,327
kWh
|
- | |
| TOTAL RECOMMENDED | $14,127 | $28,750 |
$10,271
87,339
kWh
|
$3,856
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $3,351 | $2,414 |
$3,351
44,842
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs