Assessment Year | 1995 |
---|---|
Principal Product | Design and manufacturing of electronic equipment |
NAICS |
n/a
|
SIC | 3672: Printed Circuit Boards |
Sales Range | $10 M to 50M |
# of Employees | 213 |
Plant Area |
108,000
ft2
|
Annual Production | 10
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $66,441 | 1,873,681 |
kWh
|
$0.035 |
Natural Gas | $7,419 | 1,455 |
MMBtu
|
$5.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,127 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,351 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7226: Use computer programs to optimize hvac performance | $7,900 | $25,000 |
$4,044
-
kWh
|
$3,856
-
MMBtu
|
|
02 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,638 | - |
$1,638
11,137
kWh
|
- | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $913 | $128 |
$913
13,189
kWh
|
- | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $903 | - |
$903
-
kWh
|
- | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $837 | $540 |
$837
23,447
kWh
|
- | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $749 | $112 |
$749
10,844
kWh
|
- | |
07 | 2.7135: Install occupancy sensors | $467 | $1,100 |
$467
13,189
kWh
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $387 | $684 |
$387
8,206
kWh
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $333 | $1,186 |
$333
7,327
kWh
|
- | |
TOTAL RECOMMENDED | $14,127 | $28,750 |
$10,271
87,339
kWh
|
$3,856
-
MMBtu
|
||
TOTAL IMPLEMENTED | $3,351 | $2,414 |
$3,351
44,842
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs