Assessment Year | 2016 |
---|---|
Principal Product | Sheet Metal |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 87 |
Plant Area |
75,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $110,933 | 1,491,600 |
kWh
|
$0.074 |
Electricity Demand | $15,595 | 4,393 |
kW-mo/yr
|
$3.55 |
Electricity Fees | $16,583 | - |
|
- |
Natural Gas | $118,537 | 9,896 |
MMBtu
|
$11.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $46,902 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,792 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $143 | - |
$143
1,934
kWh
|
- | - | - | - | |
02 | 2.8114: Change rate schedules or other changes in utility service | $19,792 | $25 | - | - | - | $19,792 | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,305 | $1,800 |
$6,687
90,368
kWh
|
$618
-
kW-mo/yr
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $707 | $200 |
$707
9,558
kWh
|
- | - | - | - | |
05 | 2.7135: Install occupancy sensors | $7,907 | $12,234 |
$6,988
94,427
kWh
|
$476
-
kW-mo/yr
|
- | - | $444 | |
06 | 2.1221: Replace obsolete burners with more efficient ones | $3,031 | $9,467 | - | - |
$3,031
-
MMBtu
|
- | - | |
07 | 2.4226: Use / purchase optimum sized compressor | $8,016 | $28,500 |
$7,338
99,167
kWh
|
$678
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $46,902 | $52,226 |
$21,864
295,454
kWh
|
$1,771
-
kW-mo/yr
|
$3,031
-
MMBtu
|
$19,792 | $444 | ||
TOTAL IMPLEMENTED | $19,792 | $25 | - | - | - | $19,792 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs