| Assessment Year | 2014 | 
|---|---|
| Principal Product | Welded Chains | 
| NAICS | 332618: Other Fabricated Wire Product Manufacturing | 
| SIC | 3496: Miscellaneous Fabricated Wire Products | 
| Sales Range | $10 M  to 50M  | 
    
| # of Employees | 120 | 
| Plant Area | 
                            320,000
                 
ft2
 
                     | 
    
| Annual Production | 28,100,000
             
lb
 
         | 
    
| Production Hrs. Annual | 6,240
             
hrs
 
         | 
    
| Location (State) | Pennsylvania | 
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $823,134 | 10,891,398 | 
             
kWh
 
         | 
        $0.076 | 
| Electricity Demand | $43,612 | 29,871 | 
             
kW-mo/yr
 
         | 
        $1.46 | 
| Electricity Fees | $84,360 | - | 
             | 
        - | 
| Natural Gas | $333,732 | 58,963 | 
             
MMBtu
 
         | 
        $5.66 | 
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $278,871 | 
             See individual recommendations below 
            *Non-energy impacts included in savings.
         | 
    ||
| IMPLEMENTED SAVINGS* | $21,345 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | 
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $1,880 | $36 | - | - | 
                        $1,880
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                                                                - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $5,361 | $838 | 
                        $5,180
                                                     68,160
                                 
                                            
kWh
 
                             | 
                                                                                
                        $181
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                - | - | |
| 03 | 2.2121: Increase amount of condensate returned | $19,935 | $4,735 | - | - | 
                        $19,935
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                                                                - | |
| 04 | 2.4226: Use / purchase optimum sized compressor | $95,368 | $34,500 | 
                        $92,917
                                                     1,222,594
                                 
                                            
kWh
 
                             | 
                                                                                
                        $2,451
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                - | - | |
| 05 | 2.2135: Repair and eliminate steam leaks | $3,233 | $771 | - | - | 
                        $3,233
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                                                                - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,665 | $3,500 | 
                        $4,656
                                                     61,263
                                 
                                            
kWh
 
                             | 
                                                                                
                        $5,009
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                - | - | |
| 07 | 2.2442: Preheat combustion air with waste heat | $9,549 | $5,000 | - | - | 
                        $9,549
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                                                                - | |
| 08 | 2.4226: Use / purchase optimum sized compressor | $105,416 | $79,682 | 
                        $102,706
                                                     1,351,399
                                 
                                            
kWh
 
                             | 
                                                                                
                        $2,710
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                - | - | |
| 09 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,210 | $3,000 | - | 
                        $2,210
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                - | - | |
| 10 | 2.7135: Install occupancy sensors | $6,567 | $9,190 | 
                        $5,881
                                                     77,376
                                 
                                            
kWh
 
                             | 
                                                                                
                        $435
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                - | $251 | |
| 11 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,146 | $3,000 | - | - | 
                        $1,146
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                                                                - | |
| 12 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,362 | $16,000 | - | - | 
                        $5,362
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                                                                - | |
| 13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,644 | $10,950 | 
                        $2,191
                                                     28,829
                                 
                                            
kWh
 
                             | 
                                                                                
                        $162
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                - | $291 | |
| 14 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,535 | $51,625 | 
                        $7,512
                                                     98,842
                                 
                                            
kWh
 
                             | 
                                                                                
                        $277
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                - | $2,746 | |
| TOTAL RECOMMENDED | $278,871 | $222,827 | 
                        $221,043
                                                     2,908,463
                                 
                                            
kWh
 
                             | 
                                                                                
                        $13,435
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                
                        $41,105
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                                                                $3,288 | ||
| TOTAL IMPLEMENTED | $21,345 | $13,497 | 
                        $10,537
                                                     138,639
                                 
                                            
kWh
 
                             | 
                                                                                
                        $5,444
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                
                        $5,113
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                                                                $251 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs