Assessment Year | 2013 |
---|---|
Principal Product | Lumber |
NAICS | 321999: All Other Miscellaneous Wood Product Manufacturing |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 61 |
Plant Area |
1,000,000
ft2
|
Annual Production | 6,234
Tgal
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $90,266 | 1,238,942 |
kWh
|
$0.073 |
Electricity Demand | $30,700 | 4,728 |
kW-mo/yr
|
$6.49 |
Electricity Fees | $22,853 | - |
|
- |
Natural Gas | $31,255 | 3,216 |
MMBtu
|
$9.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,456 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,549 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2443: Re-use or recycle hot or cold process exhaust air | $8,272 | $11,000 | - | - |
$8,272
-
MMBtu
|
- | |
02 | 2.7135: Install occupancy sensors | $1,506 | $6,750 |
$1,094
14,988
kWh
|
$136
-
kW-mo/yr
|
- | $276 | |
03 | 2.7135: Install occupancy sensors | $435 | $1,950 |
$316
4,330
kWh
|
$39
-
kW-mo/yr
|
- | $80 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,942 | $6,385 |
$1,352
18,520
kWh
|
$526
-
kW-mo/yr
|
- | $64 | |
05 | 2.7261: Install timers and/or thermostats | $1,398 | $115 |
$1,398
19,144
kWh
|
- | - | - | |
06 | 2.4323: Use optimum size and capacity equipment | $784 | $2,653 |
$784
10,734
kWh
|
- | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,158 | $5,700 |
$2,399
32,868
kWh
|
$759
-
kW-mo/yr
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $514 | $1,000 |
$410
5,622
kWh
|
$104
-
kW-mo/yr
|
- | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $280 | $300 |
$202
2,771
kWh
|
$78
-
kW-mo/yr
|
- | - | |
10 | 2.7135: Install occupancy sensors | $4,529 | $1,172 |
$4,529
62,042
kWh
|
- | - | - | |
11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,909 | $8,300 |
$11,333
155,244
kWh
|
$3,576
-
kW-mo/yr
|
- | - | |
12 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,729 | $8,300 |
$2,833
38,811
kWh
|
$896
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $41,456 | $53,625 |
$26,650
365,074
kWh
|
$6,114
-
kW-mo/yr
|
$8,272
-
MMBtu
|
$420 | ||
TOTAL IMPLEMENTED | $15,549 | $25,287 |
$13,181
180,576
kWh
|
$2,012
-
kW-mo/yr
|
- | $356 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs