Assessment Year | 2013 |
---|---|
Principal Product | Corrugated Shipping Containers |
NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $50 M to 100M |
# of Employees | 264 |
Plant Area |
522,000
ft2
|
Annual Production | 1,700,000
thousand feet
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $586,311 | 9,150,282 |
kWh
|
$0.064 |
Electricity Demand | $154,529 | 43,031 |
kW-mo/yr
|
$3.59 |
Natural Gas | $617,387 | 58,552 |
MMBtu
|
$10.54 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $127,970 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,532 | $10,100 |
$10,900
170,316
kWh
|
$1,632
-
kW-mo/yr
|
|
02 | 2.7135: Install occupancy sensors | $1,744 | $1,360 |
$1,744
27,256
kWh
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $10,131 | $393 |
$9,294
145,226
kWh
|
$836
-
kW-mo/yr
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,900 | $1,000 |
$4,552
71,121
kWh
|
$348
-
kW-mo/yr
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,249 | $228 |
$110
1,723
kWh
|
$1,139
-
kW-mo/yr
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,535 | $22,875 |
$16,088
251,372
kWh
|
$1,447
-
kW-mo/yr
|
|
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $23,989 | $28,700 |
$22,011
343,925
kWh
|
$1,978
-
kW-mo/yr
|
|
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $29,988 | $35,500 |
$27,514
429,907
kWh
|
$2,474
-
kW-mo/yr
|
|
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,865 | $14 |
$6,259
97,791
kWh
|
$607
-
kW-mo/yr
|
|
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,998 | $8,300 |
$5,503
85,982
kWh
|
$495
-
kW-mo/yr
|
|
11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,610 | $16,600 |
$11,569
180,768
kWh
|
$1,041
-
kW-mo/yr
|
|
12 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $429 | $294 |
$393
6,145
kWh
|
$36
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $127,970 | $125,364 |
$115,937
1,811,532
kWh
|
$12,033
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs