Assessment Year | 2012 |
---|---|
Principal Product | Milk |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
55,000
ft2
|
Annual Production | 30,000
Tgal
|
Production Hrs. Annual | 7,440
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $323,386 | 7,881,144 |
kWh
|
$0.041 |
Electricity Demand | $114,380 | 16,324 |
kW-mo/yr
|
$7.01 |
Electricity Fees | $11,473 | - |
|
- |
Natural Gas | $80,996 | 19,824 |
MMBtu
|
$4.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $80,838 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,546 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 3.3128: Utilize other methods to remove contaminants | $66,393 | $99,038 |
$(-2,024.0)
(-49,375)
kWh
|
- | $68,417 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,546 | $980 |
$7,546
184,045
kWh
|
$2,000
-
kW-mo/yr
|
- | |
03 | 2.4314: Use synthetic lubricant | $2,906 | - |
$2,171
52,948
kWh
|
$735
-
kW-mo/yr
|
- | |
04 | 2.7134: Use photocell controls | $1,384 | $520 |
$874
21,305
kWh
|
$510
-
kW-mo/yr
|
- | |
05 | 2.7135: Install occupancy sensors | $609 | $2,640 |
$609
14,846
kWh
|
- | - | |
TOTAL RECOMMENDED | $80,838 | $103,178 |
$9,176
223,769
kWh
|
$3,245
-
kW-mo/yr
|
$68,417 | ||
TOTAL IMPLEMENTED | $9,546 | $980 |
$7,546
184,045
kWh
|
$2,000
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs