Assessment Year | 2022 |
---|---|
Principal Product | Beef |
NAICS | 311611: Animal (except Poultry) Slaughtering |
SIC | 2011: Meat Packing Plants |
Sales Range | $100 M to 500M |
# of Employees | 380 |
Plant Area |
116,030
ft2
|
Annual Production | 187,714
units
|
Production Hrs. Annual | 3,650
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $519,692 | 10,027,732 |
kWh
|
$0.052 | |
Electricity Demand | $153,816 | 20,013 |
kW-mo/yr
|
$7.69 | |
Natural Gas | $605,540 | 108,425 |
MMBtu
|
$5.58 | |
Fuel Oil #2 | $19,283 | 860 |
MMBtu
|
$22.42 | |
Waste Disposal Costs | |||||
Water Usage | $289,071 | 158,740 |
Tgal
|
$1.82 | |
Water Disposal | $1,091,074 | 158,740 |
Tgal
|
$6.87 | |
TOTAL YEARLY COSTS | $2,678,476 | ||||
RECOMMENDED SAVINGS* | $417,074 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $133,088 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1224: Replace boiler | $280,847 | $220,000 |
$(-136,643.0)
(-2,643,000)
kWh
|
$(-51,650.0)
-
kW-mo/yr
|
$469,140
-
MMBtu
|
- | - | - | - | |
02 | 3.4151: Minimize water usage | $106,955 | $72,150 | - | - |
$41,854
-
MMBtu
|
$13,636
-
Tgal
|
$51,465
-
Tgal
|
- | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $21,879 | $30,410 |
$22,911
443,153
kWh
|
$(-1,032.0)
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.2437: Recover waste heat from equipment | $3,139 | $8,000 | - | - |
$3,139
-
MMBtu
|
- | - | - | - | |
05 | 2.2511: Insulate bare equipment | $2,400 | $9,724 | - | - |
$2,400
-
MMBtu
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,447 | $4,500 |
$2,267
43,852
kWh
|
- | - | - | - | $(-720.0) | $(-100.0) | |
07 | 2.2511: Insulate bare equipment | $407 | $2,521 | - | - |
$407
-
MMBtu
|
- | - | - | - | |
TOTAL RECOMMENDED | $417,074 | $347,305 |
$(-111,465.0)
(-2,155,995)
kWh
|
$(-52,682.0)
-
kW-mo/yr
|
$516,940
-
MMBtu
|
$13,636
-
Tgal
|
$51,465
-
Tgal
|
$(-720.0) | $(-100.0) | ||
TOTAL IMPLEMENTED | $133,088 | $119,305 |
$25,178
487,005
kWh
|
$(-1,032.0)
-
kW-mo/yr
|
$44,661
-
MMBtu
|
$13,636
-
Tgal
|
$51,465
-
Tgal
|
$(-720.0) | $(-100.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs