ITAC Assessment: LE0360
ITAC logo
ITAC Assessment: LE0360
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Printing/Mailing
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 160,000
ft2
Annual Production 18
units
Production Hrs. Annual 4,320
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $150,985 1,980,200
kWh
Electricity Demand $17,782 5,100
kW-mo/yr
Electricity Fees $129,423 -
Natural Gas $22,037 5,793
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,909 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,261

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,056 $8,300 $2,757
36,288
kWh
$299
-
kW-mo/yr
- - -
02 2.7135: Install occupancy sensors $16,814 $25,500 $13,829
181,961
kWh
$667
-
kW-mo/yr
- - $2,318
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,813 $6,560 $1,704
22,426
kWh
$42
-
kW-mo/yr
- - $1,067
04 2.7232: Replace existing hvac unit with high efficiency model $7,603 $29,670 $6,802
89,505
kWh
$801
-
kW-mo/yr
- - -
05 2.7447: Install vinyl strip / high speed / air curtain doors $2,262 $9,600 $2,709
35,650
kWh
- - $(-447.0) -
06 2.2437: Recover waste heat from equipment $1,806 $3,200 - - $1,806
-
MMBtu
- -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,156 $5,250 $1,912
25,155
kWh
$244
-
kW-mo/yr
- - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $366 $80 $324
4,160
kWh
$42
-
kW-mo/yr
- - -
09 2.4323: Use optimum size and capacity equipment $691 $700 $691
9,100
kWh
- - - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,342 $1,000 $2,077
27,327
kWh
$265
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $39,909 $89,860 $32,805
431,572
kWh
$2,360
-
kW-mo/yr
$1,806
-
MMBtu
$(-447.0) $3,385
TOTAL IMPLEMENTED $8,261 $13,280 $5,849
76,875
kWh
$606
-
kW-mo/yr
$1,806
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs