ITAC Assessment: LE0350
ITAC logo
ITAC Assessment: LE0350
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Custom Molded Rubber Parts
NAICS 326291: Rubber Product Manufacturing for Mechanical Use
SIC 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods
Sales Range $1
M
to 5
M
# of Employees 7
Plant Area 46,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 2,040
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,205 355,920
kWh
Electricity Demand $21,774 1,726
kW-mo/yr
Natural Gas $55,269 5,258
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,694 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,286

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,189 $3,025 - $1,189
-
kW-mo/yr
- -
02 2.7135: Install occupancy sensors $5,254 $9,913 $3,414
26,879
kWh
$1,742
-
kW-mo/yr
- $99
03 2.7142: Utilize higher efficiency lamps and/or ballasts $7,486 $11,638 $4,627
36,434
kWh
$2,701
-
kW-mo/yr
- $158
04 2.4226: Use / purchase optimum sized compressor $9,994 $15,500 $6,448
50,770
kWh
$3,546
-
kW-mo/yr
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,329 $8,800 $3,436
27,055
kWh
$1,893
-
kW-mo/yr
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,117 $2,783 $1,437
11,315
kWh
$1,680
-
kW-mo/yr
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,490 $1,000 $1,572
12,376
kWh
$919
-
kW-mo/yr
- -
08 2.4231: Reduce the pressure of compressed air to the minimum required $2,053 $600 $1,296
10,203
kWh
$757
-
kW-mo/yr
- -
09 2.4221: Install compressor air intakes in coolest locations $634 - $356
2,805
kWh
$278
-
kW-mo/yr
- -
10 2.2136: Install / repair insulation on steam lines $21 - - - $21
-
MMBtu
-
11 2.2113: Repair or replace steam traps $5,076 $1,275 - - $5,076
-
MMBtu
-
12 2.1233: Analyze flue gas for proper air/fuel ratio $3,008 $2,000 - - $3,008
-
MMBtu
-
13 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,986 $3,000 $2,727
21,469
kWh
$2,259
-
kW-mo/yr
- -
14 2.2126: Lower operating pressure of condenser (steam) $57 - - - $12
-
MMBtu
$45
TOTAL RECOMMENDED $50,694 $59,534 $25,312
199,306
kWh
$16,963
-
kW-mo/yr
$8,117
-
MMBtu
$302
TOTAL IMPLEMENTED $11,286 $4,275 $1,928
15,181
kWh
$1,196
-
kW-mo/yr
$8,117
-
MMBtu
$45
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs