Assessment Year | 2012 |
---|---|
Principal Product | Precast Concrete Parking Garages |
NAICS | 327390: Other Concrete Product Manufacturing |
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | less than $500 k |
# of Employees | 40 |
Plant Area |
1,001
ft2
|
Annual Production | 3,792
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $405,516 | 4,153,001 |
kWh
|
$0.098 |
Electricity Demand | $68,295 | 15,248 |
kW-mo/yr
|
$4.48 |
Natural Gas | $306,323 | 36,281 |
MMBtu
|
$8.44 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $212,831 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,131 | $225 |
$9,925
99,183
kWh
|
$206
-
kW-mo/yr
|
- | |
02 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $64,152 | $160,000 |
$52,822
614,218
kWh
|
$8,058
-
kW-mo/yr
|
$3,272
-
MMBtu
|
|
03 | 2.2437: Recover waste heat from equipment | $44,014 | $12,000 |
$43,355
442,395
kWh
|
$659
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $21,529 | $10,000 |
$19,790
201,938
kWh
|
$1,739
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,439 | $57,600 |
$18,786
191,693
kWh
|
$1,653
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,842 | $130,000 |
$14,965
152,705
kWh
|
$1,877
-
kW-mo/yr
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $11,030 | $40 |
$10,139
103,461
kWh
|
$891
-
kW-mo/yr
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,061 | $52,345 |
$9,246
94,348
kWh
|
$815
-
kW-mo/yr
|
- | |
09 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $9,355 | $16,675 |
$9,355
99,133
kWh
|
- | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,634 | $1,000 |
$3,338
34,065
kWh
|
$296
-
kW-mo/yr
|
- | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,644 | $8,900 |
$1,514
15,444
kWh
|
$130
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $212,831 | $448,785 |
$193,235
2,048,583
kWh
|
$16,324
-
kW-mo/yr
|
$3,272
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs