| Assessment Year | 2011 |
|---|---|
| Principal Product | Pressure Vessels |
| NAICS | 336415: Guided Missile and Space Vehicle Propulsion Unit and Propulsion Unit Parts Manufacturing |
| SIC | 3764: Guided Missile and Space Vehicle Propulsion Units and Propulsion Unit Parts |
| Sales Range | $10 M to 50M |
| # of Employees | 31 |
| Plant Area |
54,000
ft2
|
| Annual Production | 220
pieces
|
| Production Hrs. Annual | 5,460
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $144,169 | 1,252,480 |
kWh
|
$0.12 |
| Electricity Demand | $62,350 | 4,297 |
kW-mo/yr
|
$14.51 |
| Natural Gas | $15,491 | 1,368 |
MMBtu
|
$11.32 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $55,421 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $51,091 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,373 | $21,660 |
$10,207
88,759
kWh
|
$2,060
-
kW-mo/yr
|
- | $106 | |
| 02 | 2.4226: Use / purchase optimum sized compressor | $10,236 | $51,475 |
$8,016
69,707
kWh
|
$2,220
-
kW-mo/yr
|
- | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $9,313 | $108 |
$7,183
62,462
kWh
|
$1,988
-
kW-mo/yr
|
- | $142 | |
| 04 | 2.7261: Install timers and/or thermostats | $6,020 | $95 |
$6,020
52,348
kWh
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,890 | $10,580 |
$2,843
24,723
kWh
|
$784
-
kW-mo/yr
|
- | $263 | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,255 | $1,000 |
$3,123
27,158
kWh
|
$1,132
-
kW-mo/yr
|
- | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $2,949 | $500 |
$2,659
23,118
kWh
|
$290
-
kW-mo/yr
|
- | - | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,956 | $25 |
$1,463
12,722
kWh
|
$493
-
kW-mo/yr
|
- | - | |
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,818 | $1,000 |
$483
4,200
kWh
|
$1,335
-
kW-mo/yr
|
- | - | |
| 10 | 2.2437: Recover waste heat from equipment | $1,381 | $2,000 | - | - |
$1,381
-
MMBtu
|
- | |
| 11 | 2.1221: Replace obsolete burners with more efficient ones | $1,230 | $35,000 | - | - |
$1,230
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $55,421 | $123,443 |
$41,997
365,197
kWh
|
$10,302
-
kW-mo/yr
|
$2,611
-
MMBtu
|
$511 | ||
| TOTAL IMPLEMENTED | $51,091 | $120,943 |
$39,338
342,079
kWh
|
$10,012
-
kW-mo/yr
|
$1,230
-
MMBtu
|
$511 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs