Assessment Year | 2011 |
---|---|
Principal Product | Party Decorations and Novelties |
NAICS | 322299: All Other Converted Paper Product Manufacturing |
SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
800,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $145,472 | 3,651,872 |
kWh
|
$0.040 |
Electricity Demand | $159,909 | 14,146 |
kW-mo/yr
|
$11.30 |
Natural Gas | $18,683 | 8,839 |
MMBtu
|
$2.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $94,638 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $37,608 | $67,275 |
$25,613
640,358
kWh
|
$11,995
-
kW-mo/yr
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,225 | $11,500 |
$7,666
191,660
kWh
|
$5,559
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,035 | $13,000 |
$4,916
122,896
kWh
|
$7,119
-
kW-mo/yr
|
- | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,994 | $3,000 | - |
$7,994
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,230 | $25,000 |
$4,190
104,738
kWh
|
$3,040
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $2,639 | $2,250 |
$2,639
65,985
kWh
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,209 | $3,200 |
$1,853
46,331
kWh
|
$1,356
-
kW-mo/yr
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,621 | $1,120 |
$1,519
37,990
kWh
|
$1,102
-
kW-mo/yr
|
- | - | |
09 | 2.7232: Replace existing hvac unit with high efficiency model | $2,438 | $23,800 |
$1,209
30,240
kWh
|
$949
-
kW-mo/yr
|
$280
-
MMBtu
|
- | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,860 | $3,600 |
$912
22,801
kWh
|
$707
-
kW-mo/yr
|
- | $241 | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,567 | $3,205 |
$912
22,805
kWh
|
$655
-
kW-mo/yr
|
- | - | |
12 | 2.4221: Install compressor air intakes in coolest locations | $1,182 | $1,000 |
$617
15,427
kWh
|
$565
-
kW-mo/yr
|
- | - | |
13 | 2.7145: Install skylights | $1,030 | $22,500 |
$1,030
25,766
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $94,638 | $180,450 |
$53,076
1,326,997
kWh
|
$41,041
-
kW-mo/yr
|
$280
-
MMBtu
|
$241 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs