ITAC Assessment: LE0298
ITAC logo
ITAC Assessment: LE0298
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Bottled water
NAICS 312112: Bottled Water Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $50
M
to 100
M
# of Employees 150
Plant Area 350,000
ft2
Annual Production 63,500
Tgal
Production Hrs. Annual 8,400
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $707,214 20,040,062
kWh
Electricity Demand $478,314 45,861
kW-mo/yr
Natural Gas $70,217 6,510
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $132,940 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,555

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4226: Use / purchase optimum sized compressor $77,015 $56,771 $54,017
1,543,384
kWh
$22,998
-
kW-mo/yr
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $22,178 $100,000 $19,831
566,625
kWh
$2,347
-
kW-mo/yr
- -
03 2.2223: Enhance sensitivity of temperature control and cutoff $8,306 $20,000 $4,801
137,220
kWh
$3,505
-
kW-mo/yr
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,050 $2,440 $2,929
85,047
kWh
$5,121
-
kW-mo/yr
- -
05 2.4221: Install compressor air intakes in coolest locations $5,536 $6,000 $3,648
104,216
kWh
$1,888
-
kW-mo/yr
- -
06 2.7231: Use radiant heater for spot heating $4,726 $3,900 - - - $4,726
-
MMBtu
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,787 $4,200 $1,838
51,965
kWh
$949
-
kW-mo/yr
- -
08 2.3134: Shift from daytime to nighttime operation $2,423 $1,750 - - $2,423 -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $1,592 $12,000 $904
25,833
kWh
$688
-
kW-mo/yr
- -
10 2.7135: Install occupancy sensors $327 $630 $327
9,345
kWh
- - -
TOTAL RECOMMENDED $132,940 $207,691 $88,295
2,523,635
kWh
$37,496
-
kW-mo/yr
$2,423 $4,726
-
MMBtu
TOTAL IMPLEMENTED $30,555 $103,070 $23,087
661,017
kWh
$7,468
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs