Assessment Year | 2008 |
---|---|
Principal Product | Transit related components |
NAICS | 333911: Pump and Pumping Equipment Manufacturing |
SIC | 3743: Railroad Equipment |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
101,000
ft2
|
Annual Production | 100,000
lb
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $104,855 | 924,200 |
kWh
|
$0.11 |
Electricity Demand | $28,773 | 2,720 |
kW-mo/yr
|
$10.58 |
Natural Gas | $30,130 | 2,130 |
MMBtu
|
$14.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,676 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,841 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7231: Use radiant heater for spot heating | $9,502 | $3,600 | - | - |
$9,502
-
MMBtu
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,477 | $1,790 |
$5,497
48,648
kWh
|
$1,980
-
kW-mo/yr
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,659 | $5,000 |
$4,161
36,823
kWh
|
$1,498
-
kW-mo/yr
|
- | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,441 | $2,500 | - |
$1,441
-
kW-mo/yr
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $1,306 | $1,000 | - | - |
$1,306
-
MMBtu
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $923 | $240 |
$679
6,005
kWh
|
$244
-
kW-mo/yr
|
- | - | |
07 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $831 | $1,200 | - | - |
$831
-
MMBtu
|
- | |
08 | 2.4221: Install compressor air intakes in coolest locations | $696 | $800 |
$510
4,518
kWh
|
$186
-
kW-mo/yr
|
- | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $670 | $120 |
$492
4,357
kWh
|
$178
-
kW-mo/yr
|
- | - | |
10 | 2.4314: Use synthetic lubricant | $508 | $500 |
$373
3,307
kWh
|
$135
-
kW-mo/yr
|
- | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,106 | $34,067 |
$9,575
84,735
kWh
|
$3,480
-
kW-mo/yr
|
- | $51 | |
12 | 2.7135: Install occupancy sensors | $3,557 | $780 |
$3,557
31,475
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $45,676 | $51,597 |
$24,844
219,868
kWh
|
$9,142
-
kW-mo/yr
|
$11,639
-
MMBtu
|
$51 | ||
TOTAL IMPLEMENTED | $9,841 | $4,530 |
$6,176
54,653
kWh
|
$3,665
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs