| Assessment Year | 2008 |
|---|---|
| Principal Product | Plastic Closures |
| NAICS | 424130: Industrial and Personal Service Paper Merchant Wholesalers |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 110 |
| Plant Area |
190,000
ft2
|
| Annual Production | 1,500,000,000
pieces
|
| Production Hrs. Annual | 8,568
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,211,828 | 10,727,175 |
kWh
|
$0.11 |
| Electricity Demand | $90,244 | 20,334 |
kW-mo/yr
|
$4.44 |
| Natural Gas | $43,951 | 3,344 |
MMBtu
|
$13.14 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $332,881 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $162,230 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7232: Replace existing hvac unit with high efficiency model | $144,000 | $92,000 | - | - | $144,000 | - | - | - | |
| 02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $55,360 | $30,000 |
$55,067
487,318
kWh
|
$293
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.3134: Shift from daytime to nighttime operation | $38,127 | $30,600 | - | - | $38,127 | - | - | - | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $18,230 | $16,000 |
$17,222
152,410
kWh
|
$1,008
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.8113: Purchase gas directly from a contract gas supplier | $15,550 | $500 | - | - | - | - | - | $15,550 | |
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $10,749 | $16,800 | - | - | - |
$10,749
-
MMBtu
|
- | - | |
| 07 | 2.7496: Install partitions to reduce size of conditioned space | $1,838 | $3,600 | - | - | - |
$1,838
-
MMBtu
|
- | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $36,479 | $53,518 |
$33,954
300,480
kWh
|
$1,869
-
kW-mo/yr
|
- | - | $656 | - | |
| 09 | 2.7135: Install occupancy sensors | $12,548 | $600 |
$12,548
111,041
kWh
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $332,881 | $243,618 |
$118,791
1,051,249
kWh
|
$3,170
-
kW-mo/yr
|
$182,127 |
$12,587
-
MMBtu
|
$656 | $15,550 | ||
| TOTAL IMPLEMENTED | $162,230 | $108,000 |
$17,222
152,410
kWh
|
$1,008
-
kW-mo/yr
|
$144,000 | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs