Assessment Year | 2007 |
---|---|
Principal Product | Ductile iron pipes |
NAICS | 331110: Iron and Steel Mills and Ferroalloy Manufacturing |
SIC | 3321: Gray and Ductile Iron Foundries |
Sales Range | $50 M to 100M |
# of Employees | 220 |
Plant Area |
474,000
ft2
|
Annual Production | 90,000
ton
|
Production Hrs. Annual | 2,228
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,668,385 | 21,059,837 |
kWh
|
$0.079 |
Electricity Demand | $457,065 | 60,772 |
kW-mo/yr
|
$7.52 |
Natural Gas | $4,597,625 | 429,299 |
MMBtu
|
$10.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $372,234 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $88,058 | $368,500 | - |
$88,058
-
kW-mo/yr
|
- | - | |
02 | 2.7496: Install partitions to reduce size of conditioned space | $59,097 | $300 | - | - |
$59,097
-
MMBtu
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $103,515 | $150,000 |
$68,431
866,216
kWh
|
$35,084
-
kW-mo/yr
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $43,993 | $70,000 |
$29,083
285,367
kWh
|
$14,910
-
kW-mo/yr
|
- | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $25,485 | $20,000 | - | - |
$25,485
-
MMBtu
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,639 | $1,000 |
$10,338
130,865
kWh
|
$5,301
-
kW-mo/yr
|
- | - | |
07 | 2.4226: Use / purchase optimum sized compressor | $11,256 | $50,000 |
$8,961
113,413
kWh
|
$2,295
-
kW-mo/yr
|
- | - | |
08 | 2.2136: Install / repair insulation on steam lines | $9,899 | $22,894 | - | - |
$9,899
-
MMBtu
|
- | |
09 | 2.4226: Use / purchase optimum sized compressor | $6,837 | $6,837 |
$4,247
53,773
kWh
|
$1,090
-
kW-mo/yr
|
- | $1,500 | |
10 | 2.2437: Recover waste heat from equipment | $4,781 | $6,000 | - | - |
$4,781
-
MMBtu
|
- | |
11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,214 | $1,000 |
$798
10,097
kWh
|
$416
-
kW-mo/yr
|
- | - | |
12 | 2.7135: Install occupancy sensors | $2,460 | $1,200 |
$2,460
31,131
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $372,234 | $697,731 |
$124,318
1,490,862
kWh
|
$147,154
-
kW-mo/yr
|
$99,262
-
MMBtu
|
$1,500 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs