Assessment Year | 2007 |
---|---|
Principal Product | Pharmaceuticals |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
130,000
ft2
|
Annual Production | 36,000
pieces
|
Production Hrs. Annual | 3,000
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $287,124 | 3,789,744 |
kWh
|
$0.076 |
Electricity Demand | $59,461 | 9,349 |
kW-mo/yr
|
$6.36 |
Natural Gas | $186,669 | 13,921 |
MMBtu
|
$13.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $63,000 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $43,064 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $15,497 | $7,000 |
$8,504
111,900
kWh
|
$1,993
-
kW-mo/yr
|
- | $5,000 | |
02 | 2.7221: Lower temperature during the winter season and vice-versa | $15,235 | $500 |
$11,912
156,739
kWh
|
$3,323
-
kW-mo/yr
|
- | - | |
03 | 2.7232: Replace existing hvac unit with high efficiency model | $14,283 | $45,000 |
$8,536
112,320
kWh
|
$2,223
-
kW-mo/yr
|
$3,524
-
MMBtu
|
- | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $11,735 | $37,000 |
$5,745
75,600
kWh
|
$1,870
-
kW-mo/yr
|
$4,120
-
MMBtu
|
- | |
05 | 2.2625: Chill water to the highest temperature possible | $1,811 | $200 |
$1,357
17,850
kWh
|
$454
-
kW-mo/yr
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,501 | $50 |
$1,501
19,747
kWh
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,938 | $4,386 |
$2,510
33,022
kWh
|
$428
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $63,000 | $94,136 |
$40,065
527,178
kWh
|
$10,291
-
kW-mo/yr
|
$7,644
-
MMBtu
|
$5,000 | ||
TOTAL IMPLEMENTED | $43,064 | $82,700 |
$27,550
362,509
kWh
|
$7,870
-
kW-mo/yr
|
$7,644
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs