Assessment Year | 2006 |
---|---|
Principal Product | hollow fiber membrane modules |
NAICS | 325220: Artificial and Synthetic Fibers and Filaments Manufacturing |
SIC | 2824: Manmade Organic Fibers, Except Cellulosic |
Sales Range | $10 M to 50M |
# of Employees | 99 |
Plant Area |
200,000
ft2
|
Annual Production | 5,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Delaware |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $262,545 | 7,314,330 |
kWh
|
$0.036 |
Electricity Demand | $193,392 | 17,673 |
kW-mo/yr
|
$10.94 |
Natural Gas | $654,101 | 62,659 |
MMBtu
|
$10.44 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $316,385 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2423: Install waste heat boiler to produce steam | $193,808 | $200,000 | - | - | - |
$193,808
-
MMBtu
|
|
02 | 2.7232: Replace existing hvac unit with high efficiency model | $28,291 | $86,000 |
$12,905
358,445
kWh
|
$5,386
-
kW-mo/yr
|
$10,000 | - | |
03 | 2.7226: Use computer programs to optimize hvac performance | $27,533 | $20,000 |
$14,875
413,112
kWh
|
$12,658
-
kW-mo/yr
|
- | - | |
04 | 2.7229: Air condition only space necessary | $27,306 | $200 |
$19,351
537,522
kWh
|
$7,955
-
kW-mo/yr
|
- | - | |
05 | 2.7292: Lower ceiling to reduce conditioned space | $18,286 | $50,000 |
$12,901
358,351
kWh
|
$5,385
-
kW-mo/yr
|
- | - | |
06 | 2.6218: Turn off equipment when not in use | $8,730 | $2,400 |
$6,197
172,140
kWh
|
$2,533
-
kW-mo/yr
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,824 | $80 |
$4,275
118,741
kWh
|
$2,549
-
kW-mo/yr
|
- | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $2,925 | $2,000 |
$1,825
50,684
kWh
|
$1,100
-
kW-mo/yr
|
- | - | |
09 | 2.7135: Install occupancy sensors | $995 | $525 |
$995
27,631
kWh
|
- | - | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,687 | $7,500 |
$637
17,680
kWh
|
$1,050
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $316,385 | $368,705 |
$73,961
2,054,306
kWh
|
$38,616
-
kW-mo/yr
|
$10,000 |
$193,808
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs