ITAC Assessment: OR0549
ITAC logo
ITAC Assessment: OR0549
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Particleboard
NAICS 321219: Reconstituted Wood Product Manufacturing
SIC 2493: Reconstituted Wood Products
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 450,000
ft2
Annual Production 75,000
thousand feet
Production Hrs. Annual 4,160
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,514,410 31,077,581
kWh
Electricity Demand $222,316 73,620
kW-mo/yr
Electricity Fees $120,314 -
Natural Gas $1,074,620 127,055
MMBtu
Other Energy $4,866,283 448,312
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $261,217 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,482

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Energy Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 4.652: Replace existing equipment with more suitable substitutes $170,135 $100,000 - - - - $375 $800 $168,960
02 2.2442: Preheat combustion air with waste heat $46,600 $27,000 - - $46,600
-
MMBtu
- - - -
03 2.1113: Reduce combustion air flow to optimum $28,000 $700 - - $28,000
-
MMBtu
- - - -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $7,682 - $6,349
167,923
kWh
$1,333
-
kW-mo/yr
- - - - -
05 2.2136: Install / repair insulation on steam lines $8,800 $3,500 - - - $8,800
-
MMBtu
- - -
TOTAL RECOMMENDED $261,217 $131,200 $6,349
167,923
kWh
$1,333
-
kW-mo/yr
$74,600
-
MMBtu
$8,800
-
MMBtu
$375 $800 $168,960
TOTAL IMPLEMENTED $16,482 $3,500 $6,349
167,923
kWh
$1,333
-
kW-mo/yr
- $8,800
-
MMBtu
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs