ITAC Assessment: LE0232
ITAC logo
ITAC Assessment: LE0232
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product low fractional hp motors
NAICS 335312: Motor and Generator Manufacturing
SIC 3621: Motors and Generators
Sales Range $10
M
to 50
M
# of Employees 219
Plant Area 58,000
ft2
Annual Production 850,000
pieces
Production Hrs. Annual 2,340
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $144,260 1,564,500
kWh
Electricity Demand $28,938 4,807
kW-mo/yr
Natural Gas $16,157 1,376
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $112,517 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 4.426: Modify workload $35,100 $3,200 - - $35,100
02 2.7232: Replace existing hvac unit with high efficiency model $33,102 $38,465 $26,102
283,712
kWh
$7,000
-
kW-mo/yr
-
03 2.3134: Shift from daytime to nighttime operation $7,750 $3,510 $4,006
43,537
kWh
$3,744
-
kW-mo/yr
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,787 $500 $2,909
31,616
kWh
$878
-
kW-mo/yr
-
05 2.3134: Shift from daytime to nighttime operation $3,612 $620 - $3,612
-
kW-mo/yr
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $809 $60 $611
6,644
kWh
$198
-
kW-mo/yr
-
07 2.4221: Install compressor air intakes in coolest locations $363 $500 $232
2,518
kWh
$131
-
kW-mo/yr
-
08 2.7135: Install occupancy sensors $7,549 $2,440 $7,549
82,103
kWh
- -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $20,445 $51,983 $15,703
170,680
kWh
$4,742
-
kW-mo/yr
-
TOTAL RECOMMENDED $112,517 $101,278 $57,112
620,810
kWh
$20,305
-
kW-mo/yr
$35,100
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs