| Assessment Year | 2005 |
|---|---|
| Principal Product | folding cartons |
| NAICS | 322212: Folding Paperboard Box Manufacturing |
| SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
| Sales Range | less than $500 k |
| # of Employees | 77 |
| Plant Area |
102,000
ft2
|
| Annual Production | 10,358,815
units
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $164,168 | 1,539,600 |
kWh
|
$0.11 |
| Electricity Demand | $40,274 | 6,690 |
kW-mo/yr
|
$6.02 |
| Natural Gas | $55,767 | 4,919 |
MMBtu
|
$11.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $190,970 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $101,579 | $40,000 |
$86,910
812,246
kWh
|
$14,669
-
kW-mo/yr
|
- | - | |
| 02 | 2.1224: Replace boiler | $39,147 | $143,000 | - | - |
$39,147
-
MMBtu
|
- | |
| 03 | 2.4112: Install soft-start to eliminate nuisance trips | $18,895 | $42,000 | - |
$18,895
-
kW-mo/yr
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,727 | $1,000 |
$13,457
125,726
kWh
|
$2,270
-
kW-mo/yr
|
- | - | |
| 05 | 4.651: Install back-up equipment | $8,000 | $7,900 | - | - | - | $8,000 | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,005 | $500 |
$4,415
41,271
kWh
|
$590
-
kW-mo/yr
|
- | - | |
| 07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,617 | $1,200 | - | - |
$2,617
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $190,970 | $235,600 |
$104,782
979,243
kWh
|
$36,424
-
kW-mo/yr
|
$41,764
-
MMBtu
|
$8,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs