ITAC Assessment: LE0184
ITAC logo
ITAC Assessment: LE0184
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Three Piece Sanitary Food Cans
NAICS 332431: Metal Can Manufacturing
SIC 3411: Metal Cans
Sales Range less than $500
k
# of Employees 200
Plant Area 265,000
ft2
Annual Production 286,000
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $448,523 10,401,544
kWh
Electricity Demand $223,789 23,472
kW-mo/yr
Natural Gas $605,257 110,243
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $120,829 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $70,180

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.8114: Change rate schedules or other changes in utility service $35,446 - - - $35,446
02 2.6212: Turn off equipment during breaks, reduce operating time $34,434 $10,000 $34,434
802,659
kWh
- -
03 2.2625: Chill water to the highest temperature possible $15,203 $2,000 $15,203
354,375
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $11,237 - $6,903
160,532
kWh
$4,334
-
kW-mo/yr
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,137 $200 $6,617
153,882
kWh
$3,520
-
kW-mo/yr
-
06 2.4221: Install compressor air intakes in coolest locations $8,355 $1,500 $5,259
122,291
kWh
$3,096
-
kW-mo/yr
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $6,017 $30,709 $3,835
89,195
kWh
$2,182
-
kW-mo/yr
-
TOTAL RECOMMENDED $120,829 $44,409 $72,251
1,682,934
kWh
$13,132
-
kW-mo/yr
$35,446
TOTAL IMPLEMENTED $70,180 $42,409 $57,048
1,328,559
kWh
$13,132
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs