| Assessment Year | 2004 |
|---|---|
| Principal Product | Machined Metal Axles and Shafts |
| NAICS | 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $5 M to 10M |
| # of Employees | 35 |
| Plant Area |
53,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $137,632 | 1,861,900 |
kWh
|
$0.074 |
| Electricity Demand | $85,990 | 7,148 |
kW-mo/yr
|
$12.03 |
| Natural Gas | $12,828 | 1,364 |
MMBtu
|
$9.40 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $65,675 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $55,970 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $46,917 | - | - |
$46,917
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,802 | $17,364 |
$5,792
78,273
kWh
|
$3,010
-
kW-mo/yr
|
- | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $6,024 | $2,200 |
$4,179
56,481
kWh
|
$1,845
-
kW-mo/yr
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,020 | $300 |
$708
9,566
kWh
|
$312
-
kW-mo/yr
|
- | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,067 | $1,200 |
$727
9,819
kWh
|
$340
-
kW-mo/yr
|
- | |
| 06 | 2.2524: Avoid cooling of process streams or materials that must subsequently be heated | $942 | $550 | - | - |
$942
-
MMBtu
|
|
| 07 | 2.7135: Install occupancy sensors | $903 | $1,350 |
$903
12,214
kWh
|
- | - | |
| TOTAL RECOMMENDED | $65,675 | $22,964 |
$12,309
166,353
kWh
|
$52,424
-
kW-mo/yr
|
$942
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $55,970 | $4,250 |
$5,614
75,866
kWh
|
$49,414
-
kW-mo/yr
|
$942
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs