| Assessment Year | 2003 |
|---|---|
| Principal Product | Diamond and Diamond-Like Industrial Coating |
| NAICS | 339910: Jewelry and Silverware Manufacturing |
| SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
26,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $232,185 | 3,891,700 |
kWh
|
$0.060 |
| Electricity Demand | $51,988 | 7,491 |
kW-mo/yr
|
$6.94 |
| Natural Gas | $20,632 | 1,792 |
MMBtu
|
$11.51 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,637 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,710 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,980 | $1,700 | - | - |
$4,980
-
MMBtu
|
|
| 02 | 2.1321: Replace fossil fuel equipment with electrical equipment | $2,947 | $5,000 |
$(-738.0)
(-12,308)
kWh
|
$(-919.0)
-
kW-mo/yr
|
$4,604
-
MMBtu
|
|
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,194 | - |
$1,750
29,160
kWh
|
$444
-
kW-mo/yr
|
- | |
| 04 | 2.2515: Use optimum thickness insulation | $516 | $585 |
$516
8,593
kWh
|
- | - | |
| TOTAL RECOMMENDED | $10,637 | $7,285 |
$1,528
25,445
kWh
|
$(-475.0)
-
kW-mo/yr
|
$9,584
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,710 | $585 |
$2,266
37,753
kWh
|
$444
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs